Design your own

8×8 Gable Shed Plans on a Slab

This 8×8 gable shed sits on a 4″ concrete slab, with 8′ walls, a 6/12 gable roof and a peak of 10′ 4-7/8″. The 64″-wide double door opening gets a doubled header sized for the roof load above it. Rafters are 2x4 at 16″ on center. All 87 pieces of lumber are lettered below with their lengths and cuts, and the shopping list comes to 65 boards plus sheet goods and hardware.

Footprint8′ 0″ × 8′ 0″
Area64 sq ft
Height10′ 4-7/8″
Lumber87 pcs
Steps12
Checks8 pass

Open in the builderJump to the steps

3D model of the 8×8 gable shed framing

Shopping list

522x4 × 8′
52x4 × 10′
32x6 × 8′
12x6 × 10′
4PT 2x4 × 8′
107/16" OSB wall sheathing, 4×8 (10% waste)
41/2" OSB roof sheathing, 4×8 (15% waste)
3bundles shingles (0.9 squares + 10%)
1rolls synthetic underlayment
0.94cubic yards concrete (+10%)
14hurricane ties, rafter to plate

Short pieces are cut from the offcuts of longer boards. Buy one spare of each size.

Parts and cut list

Cut every part, then pencil its letter on it. The steps call parts by letter.

PartQtySizeLengthPieceHow to cut
A22x667"Header plysquare; two plies with a 1/2" plywood spacer
B22x492-5/8"Studsquare both ends
C22x492-5/8"King studsquare both ends
D12x492-1/2"Top platesquare ends; laps the next piece at the corner
E22x476-1/2"Jack studsquare both ends
F1PT 2x416"Bottom platesquare ends; laps the next piece at the corner
G1PT 2x412-1/2"Bottom platesquare ends; laps the next piece at the corner
H52x410-5/8"Cripplesquare both ends
J72x492-5/8"Studsquare both ends
K1PT 2x492-1/2"Bottom platesquare ends; laps the next piece at the corner
L12x492-1/2"Top platesquare ends; laps the next piece at the corner
M72x492-5/8"Studsquare both ends
N1PT 2x492-1/2"Bottom platesquare ends; laps the next piece at the corner
P12x492-1/2"Top platesquare ends; laps the next piece at the corner
Q22x633-1/2"Header plysquare; two plies with a 1/2" plywood spacer
R42x492-5/8"Studsquare both ends
S22x492-5/8"King studsquare both ends
T1PT 2x492-1/2"Bottom platesquare ends; laps the next piece at the corner
U12x492-1/2"Top platesquare ends; laps the next piece at the corner
V22x469"Jack studsquare both ends
W32x441"Cripplesquare both ends
X12x430-1/2"Rough sillsquare both ends
Y32x418-1/8"Cripplesquare both ends
Z42x492-1/2"Cap platelaps over the next wall at the corner
AA12x696"Ridge boardsquare both ends
AB142x468"Common rafterplumb cut 6/12 at the ridge; birdsmouth seat 1-1/2", heel 3/4"; tail plumb cut 12" past the wall
AC52x496"Rafter tietop corners cut to 6/12
AD22x421-5/16"Gable studtop cut 6/12 (26.6°), long point up
AE42x415-5/8"Gable studtop cut 6/12 (26.6°), long point up
AF42x47-5/8"Gable studtop cut 6/12 (26.6°), long point up

Step by step

New pieces are in colour with their letters. Work already done is greyed out. Open it in the builder to turn the model and print the manual.

  1. Step 1: Pour the slab

    Pour the slab

    • Form, gravel, pour a 4" slab with a thickened edge.
    • Anchor bolts 6" from every plate end and every 6 ft.

    floatlevel

  2. Step 2: Build the front wall

    Build the front wall

    A ×2 2x6 67"B ×2 2x4 92-5/8"C ×2 2x4 92-5/8"D ×1 2x4 92-1/2"E ×2 2x4 76-1/2"F ×1 2x4 16"G ×1 2x4 12-1/2"H ×5 2x4 10-5/8"

    • Lay bottom and top plates side by side on the floor.
    • Mark stud left edges from the left end (outside view): 0" · 15-1/4" · 31-1/4" · 47-1/4" · 63-1/4" · 79-1/4" · 91"
    • Frame the 64" × 78" door: kings, jacks, header.
    • Nail 2 × 16d through the plates into each stud end.
    • Equal diagonals, stand it up, plumb, brace.

    sawhammerlevelsquare

  3. Step 3: Build the right wall

    Build the right wall

    J ×7 2x4 92-5/8"K ×1 2x4 92-1/2"L ×1 2x4 92-1/2"

    • Lay bottom and top plates side by side on the floor.
    • Mark stud left edges from the left end (outside view): 0" · 15-1/4" · 31-1/4" · 47-1/4" · 63-1/4" · 79-1/4" · 91"
    • Nail 2 × 16d through the plates into each stud end.
    • Equal diagonals, stand it up, plumb, brace.

    sawhammerlevelsquare

  4. Step 4: Build the back wall

    Build the back wall

    M ×7 2x4 92-5/8"N ×1 2x4 92-1/2"P ×1 2x4 92-1/2"

    • Lay bottom and top plates side by side on the floor.
    • Mark stud left edges from the left end (outside view): 0" · 15-1/4" · 31-1/4" · 47-1/4" · 63-1/4" · 79-1/4" · 91"
    • Nail 2 × 16d through the plates into each stud end.
    • Equal diagonals, stand it up, plumb, brace.

    sawhammerlevelsquare

  5. Step 5: Build the left wall

    Build the left wall

    Q ×2 2x6 33-1/2"R ×4 2x4 92-5/8"S ×2 2x4 92-5/8"T ×1 2x4 92-1/2"U ×1 2x4 92-1/2"V ×2 2x4 69"W ×3 2x4 41"X ×1 2x4 30-1/2"Y ×3 2x4 18-1/8"

    • Lay bottom and top plates side by side on the floor.
    • Mark stud left edges from the left end (outside view): 0" · 15-1/4" · 31-1/4" · 47-1/4" · 63-1/4" · 79-1/4" · 91"
    • Frame the 30-1/2" × 26-1/2" window: kings, jacks, header.
    • Nail 2 × 16d through the plates into each stud end.
    • Equal diagonals, stand it up, plumb, brace.

    sawhammerlevelsquare

  6. Step 6: Lap the cap plates

    Lap the cap plates

    Z ×4 2x4 92-1/2"

    • Cap plates overlap every corner. That ties the walls into one box.
    • Nails every 16", two at each lap.

    hammer

  7. Step 7: Raise the ridge

    Raise the ridge

    AA ×1 2x6 96"

    • Ridge AA on temporary posts at the height shown.
    • Plumb and brace before any rafters.

    levelclamps

  8. Step 8: Set the rafters

    Set the rafters

    AB ×14 2x4 68"

    • Cut ONE pattern rafter. Check it in three places. Then cut the rest.
    • Every 16", over the studs.
    • Hurricane tie every rafter to the plate.

    speed squaresawdrill

  9. Step 9: Tie the rafters

    Tie the rafters

    AC ×5 2x4 96"

    • A tie beside every rafter pair, on the cap plates.
    • Nail each end to its rafter.

    hammer

  10. Step 10: Fill the gable ends

    Fill the gable ends

    AD ×2 2x4 21-5/16"AE ×4 2x4 15-5/8"AF ×4 2x4 7-5/8"

    • Studs every 16" from the cap up to the rafter.
    • Measure each in place. Long point up.

    speed squaresaw

  11. Step 11: Sheath the walls

    Sheath the walls

    • Sheets vertical, edges on studs, 1/8" gaps.
    • Nails 6" on edges, 12" in the middle. Cut out the openings after.

    sawnailerchalk line

  12. Step 12: Sheath the roof

    Sheath the roof

    • Long edge across the rafters, H-clips between, rows staggered.
    • Drip edge, underlayment, drip edge, shingles.

    sawnailer

The proof

Every member was sized by calculation, and the 3D model was tested piece against piece. These are the results for this plan.

✓ No two pieces occupy the same space
All 93 pieces tested pairwise as exact solids (mitres, birdsmouths, cheek cuts, notched stringers): no overlap deeper than 1/50".
✓ Every piece is connected to the ground
All 94 pieces trace a chain of contact down to the foundation.
✓ Rafters 2x4 19% used
2x4 SPF #2, span 3.94 ft, w = 43 plf total / 28 plf live
Bending: M = wL²/8 = 998 in·lb → fb = M/S = 326 psi ≤ F'b = 1736 psi  (19% used)
Shear: fv = 1.5V/A = 24 psi ≤ F'v = 155 psi  (16% used)
Deflection: 5wL⁴/384EI = 0.020" ≤ L/240 = 0.197"  (10% used)
✓ Header over door (front) 2x6 38% used
2-ply 2x6 SPF #2, span 5.58 ft, w = 161 plf total / 105 plf live
Bending: M = wL²/8 = 7524 in·lb → fb = M/S = 497 psi ≤ F'b = 1308 psi  (38% used)
Shear: fv = 1.5V/A = 41 psi ≤ F'v = 155 psi  (26% used)
Deflection: 5wL⁴/384EI = 0.039" ≤ L/240 = 0.279"  (14% used)
✓ Studs (front wall) 53% used
2x4 SPF #2, unbraced length 92.6" (le/d = 26.5 ≤ 50)
F*c = 1521 psi, FcE = 0.822·Emin/(le/d)² = 599 psi → Cp = 0.355
Capacity = Cp·F*c·A = 2831 lb ≥ load 215 lb  (8% used)
✓ Studs (back wall) 53% used
2x4 SPF #2, unbraced length 92.6" (le/d = 26.5 ≤ 50)
F*c = 1521 psi, FcE = 0.822·Emin/(le/d)² = 599 psi → Cp = 0.355
Capacity = Cp·F*c·A = 2831 lb ≥ load 215 lb  (8% used)
✓ Header over window (left) 2x6 0% used
2-ply 2x6 SPF #2, span 2.79 ft, w = 6 plf total / 4 plf live
Bending: M = wL²/8 = 70 in·lb → fb = M/S = 5 psi ≤ F'b = 1308 psi  (0% used)
Shear: fv = 1.5V/A = 1 psi ≤ F'v = 155 psi  (0% used)
Deflection: 5wL⁴/384EI = 0.000" ≤ L/240 = 0.140"  (0% used)
✓ Birdsmouth notch shear (rafters) 2x4 37% used
Heel cut 3/4" plumb leaves dn = 2.83" of the 3.5" depth over the bearing.
NDS 3.4.3.2 notched end: V'r = 2/3 · F'v · b · dn · (dn/d)² = 287 lb ≥ reaction 107 lb (37% used)

Roof: 10 psf dead + snow 0.7 × 30 = 21 psf. Rafter ties at every rafter pair stop the walls spreading (a ridge board is not a beam). Nail per IRC Table R802.5.2.

Questions

How much lumber does a 8x8 Gable Shed need?

52 2x4 × 8′, 5 2x4 × 10′, 3 2x6 × 8′, 1 2x6 × 10′, 4 PT 2x4 × 8′. 10 7/16" OSB wall sheathing, 4×8 (10% waste); 4 1/2" OSB roof sheathing, 4×8 (15% waste); 3 bundles shingles (0.9 squares + 10%).

What size rafters does a 8x8 Gable Shed need?

2x4 at 16″ on center, using 19% of their capacity at 30 psf ground snow. The bending, shear and deflection numbers are in the proof section.

How tall is it?

10′ 4-7/8″ at the peak, measured from the ground.

Do I need a permit for a 8x8 Gable Shed?

It covers 64 sq ft. The model code (IRC R105.2) exempts one-story detached accessory buildings up to 200 sq ft, and many towns set the line at 120 sq ft. Call your building department before you dig.

Can I change the size or add a door?

Yes. Open the plan in the builder, change any number, and the cuts, shopping list and checks update instantly.

Related plans

8×8 Gable Shed64 sq ft · 100 pcs · 14 steps6×10 Gable Shed60 sq ft · 98 pcs · 14 steps6×10 Gable Shed60 sq ft · 83 pcs · 12 steps6×12 Gable Shed72 sq ft · 104 pcs · 14 steps6×12 Gable Shed72 sq ft · 88 pcs · 12 steps6×8 Gable Shed48 sq ft · 86 pcs · 14 steps