8×10 Deck Plans, 30″ High

This 8′ × 10′ deck stands 30″ off the ground on posts on concrete footings. Joists are 2x6 at 16″ on center, carried by doubled 2x12 beams. The stairs and the 36″ guard are drawn and checked. All 49 pieces of lumber are lettered below with their lengths and cuts, and the shopping list comes to 44 boards plus sheet goods and hardware.

Footprint8′ 0″ × 10′ 0″
Area80 sq ft
Height2′ 6″
Lumber49 pcs
Steps6
Checks8 pass

Open in the builderJump to the steps

3D model of the 8×10 deck framing

Shopping list

3PT 2x12 × 8′
4PT 2x12 × 10′
17PT 2x6 × 8′
2PT 2x6 × 10′
1PT 4x4 × 8′
17PT 5/4x6 × 12′
0.48cubic yards concrete (+10%)
4post bases + post caps
1boxes 2-1/2" deck screws (350/box)

Short pieces are cut from the offcuts of longer boards. Buy one spare of each size.

Parts and cut list

Cut every part, then pencil its letter on it. The steps call parts by letter.

PartQtySizeLengthPieceHow to cut
A4PT 4x412-1/4"Postsquare both ends
B4PT 2x12112"Beam plysquare; 2 plies nailed together, 10d every 16" staggered
C2PT 2x6118-1/2"Rim joistsquare ends; laps the next piece at the corner
D2PT 2x694-1/2"Rim joistsquare ends; laps the next piece at the corner
E9PT 2x693"Floor joistsquare both ends
F17PT 5/4x6120"Deck boardsquare both ends
G1PT 2x1248"Stair hanger boardsquare; bolt to the rim
H4PT 2x1237-3/16"Stair stringer3 notches: rise 7-1/2", run 10-1/4"; plumb cut at the top, level cut at the bottom
J6PT 2x648"Stair treadsquare both ends

Step by step

New pieces are in colour with their letters. Work already done is greyed out. Open it in the builder to turn the model and print the manual.

  1. Step 1: Dig and pour the footings

    Dig and pour the footings

    • Stake out 4 post spots exactly where the picture shows.
    • Dig each hole Ø20" wide, below your frost line.
    • Pour concrete. Set a post base in each one, all level with a string line.

    shovelstring linelevel

  2. Step 2: Stand the posts

    Stand the posts

    A ×4 4x4 12-1/4"

    • Cut posts A to the length in the box.
    • Fix each to its base. Plumb on two faces. Brace both ways.

    sawleveldrill

  3. Step 3: Set the beams

    Set the beams

    B ×4 2x12 112"

    • Nail each pair of B plies together, 10d nails every 16", staggered.
    • Crown up. Set on the posts and fix with post caps.

    sawhammerlevel

  4. Step 4: Frame the floor

    Frame the floor

    C ×2 2x6 118-1/2"D ×2 2x6 94-1/2"E ×9 2x6 93"

    • Rims C, D around the outside, corners lapped as drawn.
    • Mark joists every 16" along the rims.
    • Joists E between the rims: 3 nails each end.
    • Measure both diagonals. Equal = square.

    sawhammersquaretape

  5. Step 5: Lay the decking

    Lay the decking

    F ×17 5/4x6 120"

    • Start at the front edge. 1/8" gap between boards (a 16d nail).
    • Two screws into every joist. Board ends only land on a joist.

    drillsawchalk line

  6. Step 6: Build the stairs

    Build the stairs

    G ×1 2x12 48"H ×4 2x12 37-3/16"J ×6 2x6 48"

    • Bolt the hanger board to the rim.
    • Lay out ONE stringer with a framing square. Test it. Cut the rest.
    • Stringers on the pad. Two screws per tread board per stringer.

    framing squaresawdrill

The proof

Every member was sized by calculation, and the 3D model was tested piece against piece. These are the results for this plan.

✓ No two pieces occupy the same space
All 49 pieces tested pairwise as exact solids (mitres, birdsmouths, cheek cuts, notched stringers): no overlap deeper than 1/50".
✓ Every piece is connected to the ground
All 54 pieces trace a chain of contact down to the foundation.
✓ Floor joists 2x6 33% used
2x6 SPF #2, span 5.75 ft, w = 67 plf total / 53 plf live
Bending: M = wL²/8 = 3306 in·lb → fb = M/S = 437 psi ≤ F'b = 1308 psi  (33% used)
Shear: fv = 1.5V/A = 35 psi ≤ F'v = 135 psi  (26% used)
Deflection: 5wL⁴/384EI = 0.045" ≤ L/360 = 0.192"  (24% used)
✓ Deck beams (2-ply) 2x12 75% used
2-ply 2x12 SPF #2, span 9.04 ft, w = 338 plf total / 270 plf live
Bending: M = wL²/8 = 41387 in·lb → fb = M/S = 654 psi ≤ F'b = 875 psi  (75% used)
Shear: fv = 1.5V/A = 68 psi ≤ F'v = 135 psi  (50% used)
Deflection: 5wL⁴/384EI = 0.081" ≤ L/360 = 0.301"  (27% used)
✓ Floor posts 4x4 19% used
4x4 SPF #2, height 1.02 ft, le/d = 3.5 ≤ 50
FcE = 34222 psi → Cp = 0.992 → capacity 16072 lb ≥ load 3052 lb (19% used)
✓ Footings 98% used
Load 3202 lb ÷ 1500 psf presumptive soil bearing = 307 in² needed
20" round footing = 314 in² (98% used). Bottom below your local frost depth.
✓ Stair geometry 97% used
4 equal risers of 7-1/2" (max 7-3/4"), 3 treads: 10-1/4" run + 1" nosing (min 10").
Notched 2x12 stringers keep 5-3/16" of wood under each notch (min 5").
✓ Stair stringers 12% used
2x12 (5.20" deep after notching) SPF #2, span 2.56 ft, w = 67 plf total / 53 plf live
Bending: M = wL²/8 = 657 in·lb → fb = M/S = 97 psi ≤ F'b = 875 psi  (11% used)
Shear: fv = 1.5V/A = 16 psi ≤ F'v = 135 psi  (12% used)
Deflection: 5wL⁴/384EI = 0.002" ≤ L/360 = 0.085"  (2% used)

Floor: 40 psf live + 10 psf dead. Footings bear on undisturbed soil below frost depth (1500 psf soil assumed). Post bases and post caps at every post.

Questions

How much lumber does a 8x10 Deck need?

3 PT 2x12 × 8′, 4 PT 2x12 × 10′, 17 PT 2x6 × 8′, 2 PT 2x6 × 10′, 1 PT 4x4 × 8′, 17 PT 5/4x6 × 12′. 0.48 cubic yards concrete (+10%); 4 post bases + post caps; 1 boxes 2-1/2" deck screws (350/box).

What size joists does a 8x10 Deck need?

2x6 at 16″ on center, using 33% of capacity at 40 psf live load.

How big do the footings need to be?

20″ round, 4 of them, bearing below your local frost line. That assumes 1,500 psf soil.

Does a 8x10 Deck need a railing?

Not by code at 30″; guards are required above 30″. You can add one in the builder.

Can I change the size or add a door?

Yes. Open the plan in the builder, change any number, and the cuts, shopping list and checks update instantly.